2018 Bond Planning Timeline

The timeline displayed on this page shows the process the Task Force underwent in creating a recommended project list to the School Board for the 2018 Bond. Links under "Associated information" will provide access to reports, presentations and more associated with the topic of each meeting.

December 8, 2016
Capital Bond Task Force begins meeting regarding the 2018 Bond.

January 5, 2017
Capital Bond Task Force met regarding the 2018 Bond and to tour North Creek High School.

January 19, 2017
The enrollment history of the district was discussed including a review of the Enrollment Demographic Task Force report to the board.

February 2, 2017
Capital Bond Planning Task Force Meeting  A review of the financial implications of past Levy and Bond amounts. Discussion of possible future bond amounts per School Board direction.

February 16, 2017
Review of Washington State's requirement for school district to perform a Building Condition Assessment.

February 28, 2017
Board Study Session to plan for the 2018 Levy and Bond amounts.

March 9, 2017
Review of Building Condition Assessment Report; establish task force parameters to recommend Building Improvement Program (BIP) projects for 2018 Bond.

March 23, 2017
Exercise to establish priorities for selection of BIP projects for the 2018 Bond.

April 6, 2017
Review, compilation and further prioritization of BIP projects determined in March 23 group exercise.

April 20, 2017
Safety & Security and Technology presentations of projects for possible inclusion in the 2018 Bond.

May 11, 2017
District Safety & Security vision and Fields Assessment presentations. Review of data collected at the April 6 meeting.

May 25, 2017
Enrollment Demographics Task Force update. Presentation of a possible new performing arts venue at Inglemoor HS. Code Requirements/Small Works and Site Circulation background and estimated costs for anticipated projects.

June 1, 2017
Phasing options for the Maltby site. Further project prioritization with a tiered approach to the possible Bond amount.

June 8, 2017
Tax rate information and Safety & Security Vision update. Project prioritization exercise to refine tiers in $25M increments over and above the $200M Board-determined parameter.

June 15, 2017
Review of finalized tiered projects highlighting distribution across the District. Developed outline of how the Task Force would present recommended projects at the Board Study Session.

June 22, 2017
Finalize the presentation for the Board Study Session.

June 27, 2017
Board Study Session to present project recommendations for 2018 Bond

August 28, 2017
Board Study Session to discuss Capital Bond and Levy

September 26, 2017
Bond & Levy status and tax rate update.

March 8, 2018
Transitions, project updates, Task Force participation.
 

Meeting Minutes | Meeting Presentations

2014 Bond Planning Meeting Minutes

October 25, 2012
Meeting Minutes | Presentation

November 15, 2012
Meeting Minutes | Presentation

December 13, 2012
Meeting Minutes | Presentation

January 10, 2013
Meeting Minutes | Presentation

February 28, 2013
Meeting Minutes | Presentation

March 14, 2013
Meeting Minutes | Presentation 

March 28, 2014
Meeting Minutes | Presentation

April 11, 2014
Meeting Minutes | Presentation

May 9, 2013
Meeting Minutes | Presentation

May 14, 2013
Meeting Minutes | Presentation

May 23, 2013
Meeting Minutes | Presentation

2010 Bond Planning Meeting Minutes

January 8, 2009
Meeting Minutes | Presentation

January 22, 2009
Meeting Minutes | Presentation

February 12, 2009
Meeting Minutes | Presentation

February 26, 2009
Meeting Minutes | Presentation

March 12, 2009
Meeting Minutes | Presentation

March 26, 2009
Meeting Minutes | Presentation

April 2, 2009
Meeting Minutes | Presentation

April 23, 2009
Meeting Minutes | Presentation